If you live within walking distance of East Colfax between Broadway and Colorado Boulevard, you've probably already heard the good news making the rounds this week: the cones are coming down. Buses are moving into the new center lanes. The stretch you've rerouted around since October 2024 is finally handing itself back.
What's easy to miss in the celebration is how small that stretch actually is against the whole project. The segment reopening this month covers roughly two miles. The full Colfax corridor, the one that will eventually carry the new "Lynx" branded buses from downtown all the way to Aurora, runs five. By the time your two miles clear, construction crews were already breaking ground on the Aurora end, and as of this past spring, work was underway simultaneously across all five segments of the line. Capitol Hill's relief is real. It is also, geographically speaking, about 40 percent of the story.
What Actually Changes This Month
The section between Broadway and Colorado Boulevard is where the two center driving lanes have been converted into dedicated, center-running bus lanes, flanked by the steel arch stations that have become the project's visual signature. Later this month, RTD buses start using those new lanes and stops. What won't show up yet: the actual Lynx buses, ticket machines, or real-time schedule displays that define full bus rapid transit service. Those come with the rest of the corridor, and full service across the entire line to Aurora is still targeted for 2027.
So the honest way to describe what's happening on your stretch of Colfax this month is a soft handoff, not a grand opening. Traffic patterns shift. The scaffolding and fencing that have blocked sidewalks and parking since construction began in October 2024, nearly two years ago now, start disappearing. But the ribbon-cutting, the new buses, the full experience the project promises, that's still more than a year out.
Why Fiction Beer Made It and Others Are Still Counting the Cost
The construction period wasn't uniformly hard on Colfax businesses, and the pattern in who struggled and who didn't says something worth knowing if you're trying to understand your own commercial strip.
Ali Hoskins-Kelly, co-owner of Fiction Beer Company, put it plainly when asked how her bar weathered nearly two years of fencing outside the front door: most of her customers were never driving down Colfax to find her in the first place.
"We've been really fortunate that so much of our clientele come from the neighborhoods, which would be north or south of Colfax. So we're really grateful that the construction hasn't hampered our business too, too much."
Compare that to the businesses that depend on Colfax itself as the draw, the drive-by and walk-by traffic that the avenue is famous for generating. Bourbon Grill, further along the corridor, hit what co-owner Mac Vo called a record low in sales during the thick of construction. Shish Kabob Grill, owned by Obeid Kaifo, sits in the segment east of Colorado Boulevard that's still mid-project, still fenced, still waiting for its own version of this month's milestone.
The lesson for anyone who pays attention to how Capitol Hill's commercial strip actually functions: a business that pulls customers off the surrounding residential blocks can absorb a lot of disruption on the avenue itself. A business that depends on the avenue as its customer pipeline cannot. That distinction will matter again whenever the next phase of construction lands on a new stretch of the corridor.
The Party the Construction Accidentally Started
Somewhere in the middle of nearly two years of detours and dust, Colfax invented its own tradition. Each time a new arch went up over a BRT station, someone threw a party.
The first one happened at Tight End, the sports bar that hosted the celebration when crews raised the earliest of the project's signature arches. The city noticed it worked and started organizing arch lift parties for the milestones that followed, drawing crowds to celebrate infrastructure the way Capitol Hill throws itself into just about everything else, with beer in hand and a reason to be outside.
Shannon Bowers has been to nearly all of them. She told Denverite the appeal isn't really about the arches themselves.
"I think the reason that I come out so often is because I get to explore little pockets of Colfax that I don't normally get to see being on the other side, being on the west side of Colorado Boulevard."
That's worth sitting with if you live in Capitol Hill and haven't been to one. The arch parties turned a construction schedule into an excuse to walk blocks of your own neighborhood you'd otherwise skip. One landed near Quebec Street this spring. Another happened right outside Fiction Beer's own door. With four of the five construction segments still active, this almost certainly isn't the last one.
What Isn't Finishing Yet
It helps to hold the whole picture at once, because the headlines this week are specific to one piece of it:
- Broadway to Colorado Boulevard: construction wrapping this month, buses moving into new center lanes
- Colorado Boulevard toward Aurora: still under active construction as of this fall
- The Aurora segment: ground broken this past spring, work just getting started
- Full corridor completion, all five segments, new Lynx buses in service: targeted for 2027
RTD's board approved the purchase of 47 new 60-foot articulated buses this past May, a $66.9 million order that signals the operational side of the project is moving forward even as the physical construction lags behind in the eastern segments. Those buses will eventually replace the existing 15 and 15L routes, two of the system's busiest, carrying a corridor that already moves close to 20,000 riders a day in its current, unglamorous form.
None of that changes what you'll notice on your block this month. It does mean that if you're picturing Colfax construction as a chapter that's closing, the more accurate picture is one segment closing while the next one opens a few blocks east.
What This Actually Means If You Live Here
The practical version: expect your stretch of Colfax to feel calmer within a few weeks, with fences down and buses running in their new lanes, but don't expect the finished product yet. No new buses, no ticket kiosks, no schedule boards. That's a 2027 milestone, not a September 2026 one.
Expect the businesses that leaned on their immediate neighborhood, the Fiction Beers of the corridor, to have come through steadier than the ones that depended on Colfax traffic itself. And if an arch goes up somewhere east of Colorado Boulevard in the coming months, there's a decent chance someone throws a party for it. Given the pattern so far, it might be worth walking over.
Capitol Hill has spent nearly two years absorbing a construction project most residents didn't ask for and can't fully see the end of yet. The part reopening this month is real progress. It's also proof that patience is still the operative word for the rest of the avenue.
If you're weighing what a changing Colfax means for property values or timing a move in Capitol Hill, The Galansky Group tracks these shifts block by block. Reach out anytime to talk through what's actually happening on the ground here, not just what the headlines say.